Calallen ISD Bond Update

STATUS OF BOND 2017 PROJECTS

PROJECT

ESTIMATED COST

TIME FRAME

FUNDING SOURCE

West Elementary at 70% on MEP & structural review.  Preliminary budgetary pricing to begin May

Unknown at this time

May 21 – July 1

GMP to August Board

2018 Bond

Science Wing at 50% on MEP & Structural review.   Preliminary budgetary pricing to begin in June

Unknown at this time

June 15 – Aug. 1

GMP to September Board

2018 Bond

Ag Expansion at 70% on MEP & Structural review.   Preliminary budgetary pricing to begin June

Unknown at this time

June 15 – Aug. 1

GMP to September Board

2018 Bond

STEM Building at 70% on MEP & Structural review.   Preliminary budgetary pricing to begin June

Unknown at this time

June 15 – Aug. 1

GMP to September Board

2018 Bond

Media Arts Building at 70% on MEP & Structural review.   Preliminary budgetary pricing to begin June

Unknown at this time

June 15 – Aug. 1

GMP to September Board

2018 Bond

Due to extensive reviews and negotiations with the City, these are the revised estimated openings of the facilities:

West Elementary opening January 2020

High School Science Center opening January 2020

AG Expansion opening January 2020

STEM Building opening January 2020

Media Arts Building opening September 2019


For more information on the Bond Projects, please click here