- Calallen Independent School District
- Bond Update
Status of Bond 2017 Projects
-
Status of Bond Projects
To view drone footage of CHS Football Field turf , please click here! Drone Footage
As of August 2019, Superintendent Arturo Almendarez updated the Board of Trustees regarding the status of the following Bond projects:
CALALLEN ISD
BOND PROJECT STATUS UPDATE
August 2019
PROJECT
FINAL COST
TIME FRAME
FUNDING SOURCE
Re-Roof 400 Hall at High School
$116,982
Complete
Nov. 2017 Bond
Ag Road
$322,895
Complete
Nov. 2017 Bond
High School Track Resurface
$513,828
Complete
Nov. 2017 Bond
High School Turf Replacement
$421,530
Complete
Nov. 2017 Bond
High School & Middle School Tennis Resurface
$142,865
Complete
Nov. 2017 Bond
High School Tennis Observation Tower Remodel
$18,700
Complete
Nov. 2017 Bond
Fuel Tank Replacement @ Transportation
$184,686
Complete
Nov. 2017 Bond
High School RTU Replacement
$517,663
Complete
Nov. 2017 Bond
High School & Middle School A Gym Bleachers
$194,745
Complete
Nov. 2017 Bond
Abate & Demo Alamo
$106,500
Complete
General Operating
High School & Middle School LED Replacement
$35,202
Complete
Nov. 2017 Bond
Ballistic Glass Upgrade All Campuses
$69,100
Complete
Nov. 2017 Bond
High School 100 Hall Exterior Door Replacement
$6,000
Complete
Nov. 2017 Bond
Water Heater Replacement at Field House
$15,000
Complete
General Operating Pool Bleacher Installation
$14,253
Complete General Operating
Pool Locker Installation
$12,437.30 Complete
General Operating Pool Radiant Heaters
$10,000 Complete
General Operating
Relocation of MS/HS DAEP to STAR
N/A
Complete
General Operating
Misc. Painting all Campuses
$45,000
Complete General Operating
Magee Front Entrance Security Remodel
$5,000
Complete General Operating
IT & Maintenance Generator
$31,310
Complete General Operating
IT Switch Replacement
$339,026.64
Complete Nov. 2017 Bond
Roof Top A/C Replacment - CHS "A" Gym, CHS "B" Gym, 100 Hall and Girls Athletics
$493,300.00
Complete Nov. 2017 Bond
PROJECT
COST (**if estimated)
TIME FRAME
FUNDING SOURCE
Expanded High School Door Access Control Systems
$162,516.58
Ongoing
Nov. 2017 Bond
High School Restroom Remodel
$100,000**
Ongoing
Nov. 2017 Bond
Magee Generator
$8,449
Ongoing
General Operating
East Walking Track
$30,000** Permit Pending
Nov. 2017 Bond
Wood River Parking Lot Repairs
$20,000** Ongoing
Nov. 2017 Bond
Roof Top A/C Replacement at Magee
$300,000** Summer 2020
Nov. 2017 Bond
Roof Top A/C Replacement at Middle School
$100,000** Summer 2021
Nov. 2017 Bond
LARGE CONSTRUCTION PROJECTS
COST
TIME FRAME
FUNDING SOURCE
West Elementary at 100% on MEP & structural review. Groundbreaking held on May 13, 2019.
$17,774,862
Guaranteed Maximum Price approved by Board on January 7, 2019
Building underway
Nov. 2017 Bond
Science Wing at 85% on MEP & Structural review. Groundbreaking held on July 15, 2019.
STEEL STRUCTURAL/COMPONENT COST $1,515,790
REMAINING BUILDING COST $8,425,567
Guaranteed Maximum Price for STEEL STRUCTURAL COMPONENTS ONLY approved by Board on January 7, 2019
Guaranteed Maximum Price approved by Board on June 12, 2019
Nov. 2017 Bond
Ag Expansion at 80% on MEP & Structural review. Preliminary budgetary pricing ongoing
PENDING
TBD Nov. 2017 Bond
Due to extensive reviews and negotiations with the City, these are the revised estimated openings of the facilities:
West Elementary projected opening August 2020
CHS Science Center projected opening August 2020
AG Expansion projected opening TBD