Status of Bond 2017 Projects

  • Status of Bond Projects as of July 2018

    Bond Update

    (View PowerPoint...click here)


    As of July 24, 2018, Superintendent Arturo Almendarez updated the Board of Trustees regarding the status of the following Bond projects:

    CALALLEN ISD

    BOND PROJECT STATUS UPDATE

     July 24, 2018 

     

    PROJECT

    ESTIMATED COST

    TIME FRAME

    FUNDING SOURCE

    Re-Roof 400 Hall at High School

    $600,000

    Aug. 15-Oct. 15

    2018 Bond

    Ag Road

    $325,000

    July 1-Sept 15

    2018 Bond

    High School Track Resurface

    $825,000

    Aug 15

    2018 Bond

    High School Turf Replacement

    $450,000

    Complete

    2018 Bond

    High School & Middle School Tennis Resurface

    $100,000

    May 15-Sept 1

    2018 Bond

    High School Tennis Observation Tower Remodel

    $20,000

    Complete

    2018 Bond

    Fuel Tank Replacement @ Transportation

    $300,000

    Complete

    2018 Bond

    High School RTU Replacement

    $577,000

    Aug 15

    2018 Bond

    High School & Middle School A Gym Bleachers

    $300,000

    Aug 15

    2018 Bond

    Abate & Demo Alamo

    $100,000

    July 1-Oct 1

    General Operating

    High School & Middle School LED Replacement

    $20,000

    Complete

    2018 Bond

    Ballistic Glass Upgrade All Campuses

    $100,000

    June 15-Oct 1

    2018 Bond

    High School 100 Hall Exterior Door Replacement

    $6,000

    Complete

    2018 Bond

    High School Door Access Control Systems

    $65,000

    Aug 15

    2018 Bond

    High School Restroom Remodel

    $100,000

    Ongoing

    2018 Bond

    Water Heater Replacement at Field House

    $15,000

    Aug 1

    General Operating

    Misc. Painting all Campuses

    $45,000

    Ongoing

    General Operating

    Magee Front Entrance Security Remodel

    $5,000

    June 25-Sept 1

    General Operating

    Pool Bleacher Installation

    $15,000

    Complete

    General Operating

    Pool Locker Installation

    $12,500

    Aug 15

    General Operating

    Pool Radiant Heaters

    $10,000

    Ongoing

    General Operating

    IT & Maintenance Generator

    $20,000

    June 1-Oct 15

    General Operating

    Magee Generator

    $20,000

    TBD

    General Operating

    Relocation of Middle School furnishings

    N/A

    Complete

    General Operating

    Relocation of Starr Staff to Middle School

    N/A

    Complete

    General Operating

    Relocation of MS/HS DAEP to Starr

    N/A

    Ongoing

    General Operating

     

    PROJECT

    ESTIMATED COST

    TIME FRAME

    FUNDING SOURCE

    West Elementary at 80% on MEP & structural review.  Preliminary budgetary pricing to begin October

    Unknown at this time

    10.21 –12.1

    GMP to January Board

    2018 Bond

    Science Wing at 70% on MEP & Structural review.   Preliminary budgetary pricing to begin in October

    Unknown at this time

    10.21 – 12.1

    GMP to January Board

    2018 Bond

    Ag Expansion at 80% on MEP & Structural review.   Preliminary budgetary pricing to begin October

    Unknown at this time

    10.21 – 12.1

    GMP to January Board

    2018 Bond

    STEM Building at 80% on MEP & Structural review.   Preliminary budgetary pricing to begin October

    Unknown at this time

    10.21 – 12.1

    GMP to January Board

    2018 Bond

    Media Arts Building at 80% on MEP & Structural review.   Preliminary budgetary pricing to begin October

    Unknown at this time

    10.21 – 12.1

    GMP to January Board

    2018 Bond

     

    Due to extensive reviews and negotiations with the City, these are the revised estimated openings of the facilities:

     

    West Elementary opening January 2020

    High School Science Center opening January 2020

    AG Expansion opening January 2020

    STEM Building opening January 2020

    Media Arts Building opening September 2019

     

     

     

     

     