Status of Bond 2017 Projects

  • Status of Bond Projects 

     

     To view a detailed pictorial status of bond projects, click here

     

    To view drone footage of CHS Football Field turf , please click here! Drone Footage

     


    As of March 2019, Superintendent Arturo Almendarez updated the Board of Trustees regarding the status of the following Bond projects:

    CALALLEN ISD

    BOND PROJECT STATUS UPDATE

    March 2019

     

    PROJECT

    FINAL COST

    TIME FRAME

    FUNDING SOURCE

    Re-Roof 400 Hall at High School

    $116,982

    Complete

    Nov. 2017 Bond

    Ag Road

    $322,895

    Complete

    Nov. 2017 Bond

    High School Track Resurface

    $513,828

    Complete

    Nov. 2017 Bond

    High School Turf Replacement

    $421,530

    Complete

    Nov. 2017 Bond

    High School & Middle School Tennis Resurface

    $142,865

    Complete

    Nov. 2017 Bond

    High School Tennis Observation Tower Remodel

    $18,700

    Complete

    Nov. 2017 Bond

    Fuel Tank Replacement @ Transportation

    $184,686

    Complete

    Nov. 2017 Bond

    High School RTU Replacement

    $517,663

    Complete

    Nov. 2017 Bond

    High School & Middle School A Gym Bleachers

    $194,745

    Complete

    Nov. 2017 Bond

    Abate & Demo Alamo

    $106,500

    Complete

    General Operating

    High School & Middle School LED Replacement

    $35,202

    Complete

    Nov. 2017 Bond

    Ballistic Glass Upgrade All Campuses

    $69,100

    Complete

    Nov. 2017 Bond

    High School 100 Hall Exterior Door Replacement

    $6,000

    Complete

    Nov. 2017 Bond

    Water Heater Replacement at Field House 

    $15,000

    Complete

    General Operating

    Pool Bleacher Installation

    $14,253

    Complete

    General Operating

    Pool Locker Installation

    $12,437.30

    Complete 

    General Operating

     Pool Radiant Heaters

    $10,000

    Complete

    General Operating 

     Relocation of MS/HS DAEP to STAR

    N/A

    Complete

    General Operating 

     

     

     

     

    PROJECT

    COST (**if estimated)

    TIME FRAME 

    FUNDING SOURCE

    Expanded High School Door Access Control Systems

    $162,516.58

    Ongoing

    Nov. 2017 Bond

    High School Restroom Remodel 

    $100,000**

    Ongoing

    Nov. 2017 Bond

    Misc. Painting all Campuses

    $45,000**

    Ongoing

    General Operating

    Magee Front Entrance Security Remodel

    $5,000**

    Ongoing

    General Operating

    IT & Maintenance Generator

    $31,310

    TBD

    General Operating

    Magee Generator

    $8,449

    June 1

    General Operating

     IT Switch Replacement Project

    $339,026.64

    August 1

    Nov. 2017 Bond

    East Walking Track

    $30,000**

    August 1

    Nov. 2017 Bond

    Wood River Parking Lot Repairs

    $20,000**

    August 1

    Nov. 2017 Bond

    Roof Top A/C Replacement - CHS "A" Gym, "B" Gym, 100 Hall and Girls Athletics

    $500,000**

    August 1

    Nov. 2017 Bond

    Roof Top A/C Replacement at East Elementary

    $100,000**

    August 1

    Nov. 2017 Bond

    Roof Top A/C Replacement at Magee

    $300,000**

    August 1

    Nov. 2017 Bond

    Roof Top A/C Replacement at Middle School

    $100,000**

    August 1

    Nov. 2017 Bond 

     

    LARGE CONSTRUCTION PROJECTS

    COST

    TIME FRAME

    FUNDING SOURCE

    West Elementary at 100% on MEP & structural review.         Waiting on permitting by City of Corpus Christi

    $17,774,862

    Guaranteed Maximum Price approved by Board on January 7, 2019 

    Nov. 2017 Bond

    Science Wing at 85% on MEP & Structural review.                Preliminary budgetary pricing ongoing

    STEEL STRUCTURAL

    COMPONENT COST    $1,515,790

    Guaranteed Maximum Price for STEEL STRUCTURAL COMPONENTS ONLY approved by Board on January 7, 2019  

    Guaranteed Maximum Price for remainder of structure to Board in May

    Nov. 2017 Bond

    Ag Expansion at 80% on MEP & Structural review.          Preliminary budgetary pricing ongoing

    PENDING

    TBD

    Nov. 2017 Bond

     

    Due to extensive reviews and negotiations with the City, these are the revised estimated openings of the facilities:

     

    West Elementary projected opening January 2020

    CHS Science Center projected opening August 2020

    AG Expansion projected opening TBD

     

     

     

     

     

     

     